Year |
Milestone |
2014 |
Commercial date of operation (CoD) officially effected on January 1 |
2013 |
Production trail run and completion of project phase on December 30 |
2010 |
Contract for supply and erection of electrical, control and automation works signed with ABBL on March 25-26 |
|
Contract for plant mechanical erection and fabrication works signed with Ayoki Fabricon Private Ltd. on June 25 |
2009 |
Contract for supply of main cement plant and machinery starting from crushing plant to packing plant signed with Humboldt Wedag Private Ltd. on September 9 |
|
Contract for plant civil construction works signed with Petron Civil Engineering Private Ltd. signed on November 20 |
2005-2006 |
RGoB and GoI decided to re-activate the DCP |
2002 |
Techno-economic friendly feasibility report for 0.5 million Tpa cement project was prepared by Holtec |
2001 |
Construction of cement plant suspended indefinitely in January due to security problems |
1992 |
Cement Corporation of India and Planning Commission, GoI completed the revised techno-economic feasibility report on DCP |
1985 |
Detailed feasibility report on the Dungsam Cement Project (DCP) for 1500 tpd was completed by Cement Corporation of India Limited |
1982 |
Geological investigation of limestone deposits in Nganglam was initiated under the supervision of the then Penden Cement Authority, Gomtu |